 OPERATION & MAINTENANCE
Rotation of the machine should always be as per the arrow mark shown.
Use the Hammers of equal weights opposite each other to avoid any vibration.
Before starting every day, pour 100 ml. lubricating oil in all the Bearings of Mill & Blower.
Blower Empeller to be checked once in a week and bolts & nuts tightened if necessary. Empeller to be replaced as per the wear & tear condition.
Cleaning of Grinding Chamber and Pipe Lines through the inspection windows to be done once is a week.
Chamber of Gear Box for Automatic Feeding Arrangement should be filled with lubricating oil upto the level so that the worm & gear run partially dipped in oil.
Bearing of Gear Box to be greased once in a month.
Cleaning of twelve fineness regulating windows, circulating rings & clamps to be done once in a month.
Light greasing of Bearings to be done once in a month.
Every Nuts & Bolts, pins of the Hammers of the machine to be minutely checked before starting the machine.
Pipe Lines and Cloth Tubes to be cleaned by light hammering.
Grinding Chamber is lined with 20 pcs. Liners and 8 pcs. Side Liners bolted with double nuts. It should be replaced if and when required.
Cloth Tubes fitted in the Cyclonic Cone should be washed and dried once in a month.